Client
Federal Republic of Germany represented by the Foreign Office
Processing period
2015 - 2022
Performance
General planning of the extension and refurbishment work; work stages 1 - 8 of the Schedule of Services and Fees for Architects and Engineers (HOAI)
Measures taken
Due to the tense security situation in West Africa, this construction work was necessary to reinforce the material security of the embassy. Replacement of the enclosing wall and the exterior guard rooms, replacement of the security elements and measures for preventive fire safety. Some areas of the building need additional refurbishment. Parallel extension work and partial refurbishment are being carried out. The raising of the enclosing wall, street protective measures and the construction of a barrier in front of the entrance were already implemented as immediate measures by a task force.