Basic refurbishment and alterations to the office building of the German Embassy in Dublin, Ireland Entrance to the embassy

Client

Federal Republic of Germany represented by the Foreign Office

Processing period

2012 - 2022

Gross external area

approx. 301.000 m2

Performance

General planning and project supervision
Work stages 1 - 9 of the Schedule of Services and Fees for Architects and Engineers (HOAI)

Use

Administrative building with increased security requirements

Measures taken

  • Replacement of the aluminium curtain facade including the thermal insulation

  • Renewal of the flat roof structure

  • Alteration work in the embassy offices including fire protection enhancement and alterations to the outdoor facilities

  • Replacement of the building services installations

Eingangsbereich der BotschaftLageplanStaircaseFacadeBathroomBadVisaschalter - SchnittVisaschalter und Diskretionskabinen